When you finish approving time sheets and the pay period is ready to be exported, it's recommended that you finalize the pay period for two reasons;

  1. To restrict the pay period modification from individuals.

  2. To protect the dates included in the pay period if you ever change the frequency of your future pay periods

IMPORTANT: Only an Administrator can modify the status of a pay period (Open, Closed, Finalized)

To do so, you can simply click on the link found next to the dates of the pay period. See below:

If you want to modify a pay period that is already finalized, see this article!